We have now completed phase 2 of the polycrub build of installing the hoops and perlins. Once the ground works were complete and the posts cemented into place the next job was to cut the posts to a set, level height.

Once cut down the hoops then had to be cut to size to match the heights of the post above the concrete level and they are then slotted over the posts.


The next phase was to attach the perlins the the twin wall polycarbonate will finally be attached to.



It was then to getting the weather boards attached to the sides below the bottom perlins.



Next phase is to attach the polycarbonate sheets and jointing strips along the length of the polycrub.